Gold Star Memorial Bridge
Frequently Asked Questions

The Connecticut Department of Transportation is committed to engaging stakeholders like you throughout the project. The questions here are some of the most frequently asked questions. However, don't hesitate to contact the Gold Star Memorial Bridge team with additional questions or queries. We'd love to hear from you!

 

What is the Gold Star Memorial Bridge?

The Gold Star Memorial Bridge consists of Northbound and Southbound structures carrying Interstate 95 over the Thames River, New England Central Railroad, Providence and Worcester Railroad, and local roads in New London and Groton.

 

Why are these projects necessary?

The Gold Star Memorial Bridges need rehabilitation to address the poor conditions of the Northbound deck and bridge steel superstructure, and to ensure that the structures continue to safely carry passenger vehicles and legal trucks, as well as oversized/overweight vehicles, which are currently restricted from using the bridges, well into the future.

 

When will I start to see construction on the Gold Star Memorial Bridge?

Steel Strengthening of the Northbound Bridge: Construction is already in progress. 

Rehabilitation of the Northbound Bridge: Construction to begin in June of 2025. 

Steel Strengthening of the Southbound Bridge: Construction is expected to begin in July of 2025.

Pedestrian Improvements: Construction is expected to begin in May of 2026.

 

How long will construction take?

Construction is already in progress on the Steel Strengthening of the Northbound Bridge (Project 0094-0256), on schedule for June 2025. Steel Strengthening of the Southbound Bridge (Project 0094-0268) will precede Pedestrian Improvements (Project 0094-0267) and Rehabilitation of the Northbound Bridge (Project 0094-0235) due to the crossover. All of the projects will wrap up by Fall of 2029.

 

Will I-95 be impacted by construction?

Impacts will occur as detailed in the What’s Happening Near You section, located on the home page.

 

What if I have a question or concern regarding the Gold Star Memorial Bridge?

Comments or questions can be submitted via email at: DOT.GoldStarBridgeProjects@ct.gov