Major Intersection Improvements on Route 202 with Silvermine and Elbow Hill Roads
The allowable work hours are as follows:
Traffic Operations
The contractor will not be allowed to perform any work that will interfere with the existing number of lanes of traffic on:
Monday thru Sunday between 7:00 a.m. to 9:00 a.m. and between 4:00 p.m. to 7:00 p.m.
Monday thru Friday between 7:00 a.m. to 7:00 p.m.
Saturday and Sunday between 10:00 a.m. and 8:00 p.m.
During the full depth reconstruction of U.S. Route 202 between Sta. 16+00 and Sta. 22+00, the Contractor will be allowed to maintain and protect at least one-way alternating traffic operations beginning at 7:00 p.m. on a Friday until 7:00 a.m. the following Monday, except during a Holiday weekend.
Traffic may be halted to expedite construction for up to ten (10) minutes from 12:01 a.m. thru 5:00 a.m.
Construction signs, uniformed Traffic control personnel and Local Police will be utilized for traffic control.
Motorists are advised to abide by the posted speed limit and expect traffic delays.