Project # 4-123
F.A.P. 0014-(169)
Town of Avon,
Route 44
Safety and Traffic Operational Improvements on
(
These construction activities are part of a $13.2 million dollar contract that will be constructed by Spazzarini Construction Company, Inc of
The Project consists of widening of Route 44 from approximately 500 feet east of the intersection with Route 10 easterly to the West Hartford –
Construction Sequence:
The first stage of construction includes installation of construction signs, surveying and layout work and tree clearing operations all along Route 44. These operations will begin the week of April 21st.
During this first stage of the Contractor will begin catch basins and drainage structures installations at various locations along Rte. 44 westbound.
Once these installations are complete, Spazzarini will start construction on the new box culverts and drainage channels along the westbound side of Rte. 44 at
During this stage of construction temporary concrete barrier curb will be installed along Rte. 44 westbound permanently closing the right lane in the vicinity of
Traffic Operations:
Motorists can expect lane closures at all times, in either direction along this section of Route 44 from April 18, 2008 until the contract completion date of November 29, 2010.
Only one lane of traffic in each direction will be available while construction is proceeding including peak travel hours.
Construction signs and Local Police will be utilized for traffic control.
Motorists are advised to reduce their speed accordingly through the work zone