CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7456 |
FOR RELEASE: October 2 , 2009 |
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot |
The project consists of the milling and resurfacing of the travel lanes from exit 25 (Route 3,
Special Advisory
The contractor is scheduled to be paving one lane at a time and there will be a taper along the edge to allow vehicles to move across lanes. However, motorists are cautioned to reduce speeds in the area and stay in lanes unless passing or exiting.
Motorists can expect lanes closures as follows:
I-91 NB Monday – Thursday 6 p.m. to 6 a.m. Friday 7 p.m. to 10 a.m. Saturday from 1 p.m. to Monday 6 a.m.
I-91 SB Monday – Thursday 7 p.m. to 6 a.m. Friday 7 p.m. to 7 a.m. Saturday Saturday from 1 p.m. to 3 p.m. on Sunday Sunday from 7 p.m. to 6 a.m. Monday
The contract, DOT Project no. 0118-0162, was awarded on September 18, 2009 to Empire Paving, Inc. of
For more information on the American Recovery and Reinvestment Act of 2009 (ARRA) and a full listing of Connecticut DOT ARRA projects, please go to our website www.ct.gov/dot under the "Recovery Information" icon in the right-hand margin.