Repairs to the
The Connecticut Department of Transportation is announcing the start of work for repairs to the
The contract was awarded to Middlesex Corporation on September 9, 2009 at a cost of $5,787,822.00 and scheduled to be completed by November 30, 2010. The Project consists of repairs to the concrete bridge deck, structural steel and bridge drainage. Lane closures can be expected on local roads starting the week of October 26, 2009. The Contractor will not being doing any work on I-95 until after March 1, 2010. The allowable hours of work are: