CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7456 |
FOR RELEASE: June 10, 2010 |
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot |
Rescheduling of Nighttime closure at Route 15 southbound Exit 87 (Brainard Road Off-Ramp) in Hartford
The Connecticut Department of Transportation is announcing that the June closure of the Route 15 southbound Exit 87 (Brainard Road off ramp) has been rescheduled to Friday, June 18, 2010, between the hours of 6 P.M. and 9 A.M. for the completion of ramp reconstruction and final paving. Friday, June 25, 2010 will also be included if weather conditions impact the scheduled night closure.
Route 15 Southbound Exit 87 Detour Information
I-91 southbound to Exit 26, Old Wethersfield, redirected onto I-91 northbound to the Brainard Road Exit (Exit 27).
DOT Project No. 0063-0561 was awarded to Arborio Corporation Contractors of Cromwell, CT at a cost of $5.1 million and is scheduled to be completed in August 2010.