The project involves the replacement of the existing expansion joint systems and includes some concrete header repairs on twelve bridges. The location of the bridges are as follows:
Site |
Bridge No. |
Town |
Location |
1 |
5494 |
Southington |
Ramp 834 from 84 west to I-691 east |
2 |
5514 |
Southington |
I-691 west off ramp to 84 east |
3 |
00371A |
Hartford |
Rt 2 over I-91, CT River and CT Southern Railroad |
4 |
05844B |
E. Hartford |
I-84 EB HOV over Rt 15 & Silver Lane off ramp |
5 |
06109 |
E. Hartford |
Rt 2 WB over East River Drive |
6 |
06110 |
E. Hartford |
Rt 2 EB over East River Drive |
7 |
06281 |
Manchester |
I-84 west ramp to I-291 north |
8 |
05686 |
Manchester |
I-384 WB over I-84 |
9 |
05580 |
Manchester |
I-84 over Hockanum River |
10 |
05782 |
Manchester |
I-384 ramp to I-291 North and I-84 East |
11 |
05558 |
Manchester |
I-384 ramp from Cemetary Rd to I-384 east |
12 |
1469A |
Hartford |
I-91 NB over Railroad and Park River Conduit |
LANE CLOSURE INFO
All sites except those noted below
Monday – Friday from 6 p.m. to 6 a.m. and 9 a.m. to 3 p.m.
I-84 east and west over the Hockanum River in Manchester (Site 9)
Monday – Thursday from 6 p.m. to 6 a.m. and 9 a.m. to 3 p.m.
Friday – 9 a.m. to 2 p.m. and Friday to Saturday from 7 p.m. to 9 a.m.
I-91 North in Hartford (Site 12)
Monday – Friday from 6 p.m. to 6 a.m. and 9 a.m. to 3 p.m.
Special advisory (Site 12) - Weekend work April 13, 2012 from 6 p.m. Friday to 6 a.m. Monday with work to be completed the weekend of April 29, 2012. The work will require reducing I-91 northbound traffic to one lane. Additional information will be provided two weeks prior to weekend work at this site.
DOT Project No 0171-0351 was awarded to Arborio Corporation of Cromwell, CT on January 27, 2012, at a cost of $1,529,995.00 and is scheduled to be completed in August 2012.