CONNECTICUT DEPARTMENT OF TRANSPORTATION
NEWS RELEASE
2800 BERLIN TURNPIKE P.O. BOX 317546
NEWINGTON CONNECTICUT, 06131-7546 |
FOR RELEASE: November 17, 2014 |
FOR FURTHER INFORMATION:
OFFICE OF COMMUNICATIONS
TELEPHONE: (860) 594-3062
FAX: (860) 594-3065
WEB SITE: www.ct.gov/dot |
Installation of New Traffic Control Signals at 11 Locations
The Department of Transportation (Department) is developing plans to install new traffic control signal equipment at 11 locations in the towns/cities of Clinton, Groton, Mansfield, Middletown, North Stonington, Norwich and Old Saybrook. The following intersections are included:
Project No. 172-423:
Clinton - Route 1 at Grove Street and North High Street (Intersection No. 027-201)
Groton – Route 184 at Kings Highway and Wal-Mart Drive (Intersection No. 058-220)
Groton – Route 349 at Meridian Street at CBS Highway (Intersection No. 058-225)
Groton – Route 1 at SR 614 (Allyn Street) (Intersection No. 058-249)
Groton – Route 1 at Maxson Road and Drive to Lighthouse Square (Intersection No. 058-251)
Mansfield – Route 195 at School Crossing (Whitney Hall) (Intersection No. 077-218)
Middletown – Route 9 at Route 154 and SR 410 (Intersection No. 082-201)
North Stonington – Route 49 at I-95 SB off-ramp and SR 617 (Intersection No. 101-206)
Norwich – SR 642 at Norwichtown Mall Drive (Intersection No. 103-242)
Groton – Route 184 at Kings Highway and Wal-Mart Drive (Intersection No. 058-220)
Groton – Route 349 at Meridian Street at CBS Highway (Intersection No. 058-225)
Groton – Route 1 at SR 614 (Allyn Street) (Intersection No. 058-249)
Groton – Route 1 at Maxson Road and Drive to Lighthouse Square (Intersection No. 058-251)
Mansfield – Route 195 at School Crossing (Whitney Hall) (Intersection No. 077-218)
Middletown – Route 9 at Route 154 and SR 410 (Intersection No. 082-201)
North Stonington – Route 49 at I-95 SB off-ramp and SR 617 (Intersection No. 101-206)
Norwich – SR 642 at Norwichtown Mall Drive (Intersection No. 103-242)
Project No. 172-424:
Norwich – Route 2 and Route 32 at SR 642 and Route 169 (Intersection No. 103-216)
Old Saybrook – Route 1 at Elm Street (Intersection No. 105-206)
Old Saybrook – Route 1 at Elm Street (Intersection No. 105-206)
It is the Department’s policy to
keep persons informed and involved when such projects are undertaken. It is important that the community share its
concerns with us to assist in the project’s development. At this time, it is anticipated that an informational
meeting or formal public hearing will not be necessary.
The design plans for the project
are expected to be completed in February 2015 and the project is tentatively
advertised for construction in May 2016.
Anyone
interested in requesting information on this project may do so by contacting
Mr. Sunny D. Ezete, P.E., Project Manager at (860) 594-2725. Please make reference to Project Nos. 172-423
and 172-424.