DOT Project 133-94 was awarded to Mattern Construction Co. on May 2, 2014, at a cost of $869,988 and is scheduled to be completed in January 2015.
LANE CLOSURE INFO-
The contractor working hours are from 7am to 3:30pm.
Route 207 (North Main Street)
The contractor will maintain a minimum of one lane of traffic in each direction except when the contractor is actively working, at which time an alternating one-way traffic operation will be maintained with temporary traffic signals.
The contractor will be allowed to halt traffic for a period not to exceed ten minutes for the installation and removal of the temporary precast concrete barrier curb.