Rescheduled Closure of Route 25 in Monroe for Bridge Construction Activities
The Connecticut Department of Transportation has rescheduled the closure of Route 25 in Monroe to facilitate construction activities on Bridge 02220 and Bridge 02219. The road closure is scheduled from Friday, August 10, 2018, at 8:00 PM, to Monday, August 13, 2018, at 6 AM, weather permitting.
Lane Closure and Detour Information
Northbound:
Right on to Monroe Turnpike (Route 111) 7.6 miles to Route 34.
Left on Route 34 5.0 miles to Wasserman Way.
Left on Wasserman Way 1.7 miles to route 25.
Right on to Monroe Turnpike (Route 111) 7.6 miles to Route 34.
Left on Route 34 5.0 miles to Wasserman Way.
Left on Wasserman Way 1.7 miles to route 25.
Southbound:
Left on Wasserman Way 1.7 miles to route 34.
Right on Route 34 5.0 miles to Monroe Turnpike (Route 111).
Right on Monroe Turnpike (Route 111) 7.6 miles to Route 25.
Left on Wasserman Way 1.7 miles to route 34.
Right on Route 34 5.0 miles to Monroe Turnpike (Route 111).
Right on Monroe Turnpike (Route 111) 7.6 miles to Route 25.
All business access for properties located within the construction zone will remain open, though traffic may only be able to access from one direction or the other on Rte 25 during the weekend closures.
The project involves the replacement of two box culverts, installation of new drainage and a water main, and associated road repairs and paving the sections of Route 25.
DOT Project No. 0084-0099 was awarded to C.J. Fucci, Inc. of New Haven, CT on January 22, 2018 at a cost of $5,594,999.98 and is scheduled for completion on August 31, 2019.