Resurfacing and Safety Improvement Project Resuming on Route 15 (Merritt Parkway) in Stamford and New Canaan 
The Connecticut Department of Transportation is announcing that construction will be resuming on Route 15 in Stamford and  New Canaan from the Greenwich town line just north of Exit 31, North Street, to the vicinity of Exit 37, Route 124 (South Avenue), on August 6, 2018. 
The project started in August of 2013, and consists of 6.5 miles of roadway resurfacing, safety improvements, and landscaping enhancements.  The work also includes rehabilitation of five historic bridges over Route 15.
DOT Project No. 0135-0270 was awarded to O&G Industries at a cost of $53,031,742.62 on July 23, 2013, and was scheduled to be completed by September, 2018.  The work is being administered by the State of Connecticut District 3 Office of Construction.

Lane Closure and Detour information

Route 15 NB       
Monday-Thursday 8 PM to 6 AM
Friday from 8 PM to 11 AM Saturday
Saturday from 7 PM to 10 AM Sunday
Sunday from 8 PM to 6 AM Monday
Route 15 SB
Monday-Friday from 7 PM to 6 AM
Friday from 7 PM to 9 AM Saturday 
Saturday from 7 PM to 10 AM Sunday
Sunday from 9 PM to 6 AM Monday
Ramp Areas
Monday – Friday 10 AM TO 2 PM and 7 PM to 6 AM
Other Roadways
Monday – Friday 9 AM to 3 PM and 6 PM to 6 AM
Saturday and Sunday from 6 PM to 10 AM