Applicant: University of Connecticut, John Dempsey Hospital

Proposal: Increase licensed bed capacity

Docket number: 32699

Application date: 2/7/2024

Current status: OHS held a hearing at the request of the applicant and limited intervenor Bristol Hospital. Supplemental information was requested via Order for Late Files.

Next steps: The applicant and limited intervenor will submit responses by July 26. Once OHS has determined the responses answer the questions in the Order for Late Files, OHS will close the hearing record and either draft a decision or begin negotiations for an agreed settlement.

Next due date: Applicant and Intervenor – July 26, 2024

__________

Applicant: Sound Recovery Services

Proposal: Establishing new behavioral health facility

Docket number: 32702

Application date: 2/29/2024

Current status: The Applicant is drafting responses to a first completeness letter requesting additional information.

Next steps: OHS will review the applicant's responses to the first completeness letter.

Next due date: 5/24/2024

__________

Applicant: Yale New Haven Hospital

Proposal: Acquiring imaging equipment (MRI and PET-MR)

Docket number: 32705

Application date: 3/14/2024

Current status: The Applicant is drafting responses to a first completeness letter requesting additional information.

Next stepsOHS will review the applicant's responses to the first completeness letter.

Next due date: 6/11/2024

__________

Applicant: SISU Integrated Health, LLC

Proposal: Establishing new behavioral health facility

Docket number: 32709

Application date: 4/16/2024

Current status: The Applicant is drafting responses to a first completeness letter requesting additional information.

Next steps: OHS will review the applicant's responses to the first completeness letter.

Next due date: 7/14/2024

__________

Applicant: MidState Medical Center

Proposal: Increasing licensed beds

Docket number: 32657

Application date: 7/27/2023

Current status: The hearing record is closed and OHS is either drafting a decision or negotiating an agreed settlement with the Applicant.

Next steps: OHS will either issue a decision or agreed settlement.

Next due date: 5/21/2024

__________

Applicant: Greenwich Hospital

Proposal: Termination of services by a hospital

Docket number: 32656

Application date: 7/25/2023

Current status: The hearing record is closed and OHS is either drafting a decision or negotiating an agreed settlement with the Applicant.

Next steps: OHS will either issue a decision or agreed settlement.

Next due date: 6/30/2024

__________

Applicant: Danbury Proton

Proposal: New technology to the state

Docket number: 32678

Application date: 11/7/2023

Current status: The hearing record is still open while the Applicant submits late files.

Next steps: OHS will close the record and move to a decision or agreed settlement negotiations.

Next due date

__________

Applicant: Johnson Memorial Hospital

Proposal: Establishing an outpatient surgical facility

Docket number: 32692

Application date: 12/21/2023

Current status: OHS will hold a hearing on 5/22/2024.

Next steps: After a hearing, the Applicant may be required to submit additional information before the record is closed.

Next due date: 5/22/2024

__________

Applicant: Bridgeport Hospital

Proposal: Acquiring a new MRI scanner

Docket number: 32673

Application date: 10/24/2023

Current status: OHS is either drafting a decision or negotiating an agreed settlement with the Applicant.

Next steps: OHS will either issue a decision or agreed settlement.

Next due date: 6/6/2024

__________

Applicant: Affect Provider Group

Proposal: Establishing new behavioral health facility

Docket number: 32662

Application date: 11/2/2023

Current status: OHS will hold a hearing on 6/12/2024.

Next steps: After a hearing, the Applicant may be required to submit additional information before the record is closed.

Next due date: 6/12/2024

__________

Applicant: Recovery 12 Solutions

Proposal: Establishing new intensive outpatient program

Docket number: 32688

Application date: 11/9/2023

Current status: OHS is either drafting a decision or negotiating an agreed settlement with the Applicant.

Next steps: OHS will either issue a decision or agreed settlement.

Next due date: 6/19/2024

__________

Applicant: Stamford-Health Norwalk Radiology, LLC

Proposal: Acquiring a new MRI scanner

Docket number: 32691

Application date: 12/14/2023

Current status: OHS is either drafting a decision or negotiating an agreed settlement with the Applicant.

Next steps: OHS will either issue a decision or agreed settlement.

Next due date: 6/23/2024

__________

Applicant: Connecticut Children’s Medical Center

Proposal: Acquiring a new CT scanner

Docket number: 32616

Application date: 12/20/23

Current status: OHS will hold a hearing on 6/25/2024.

Next steps: After a hearing, the Applicant may be required to submit additional information before the record is closed.

Next due date: 6/25/2024

__________

Applicant: Lantana Recovery of CT

Proposal: Establishing a new day treatment and outpatient program

Docket number: 32693

Application date: 1/4/2024

Current status: OHS is either drafting a decision or negotiating an agreed settlement with the Applicant.

Next steps: OHS will either issue a decision or agreed settlement.

Next due date: 7/14/2024

__________

Applicant: Mulligan Recovery Centers of CT

Proposal: Establishing a new substance abuse treatment facility

Docket number: 32664

Application date: 2/1/2024

Current status: OHS is in a 30-day waiting period to see if members of the public demand a hearing.

Next steps: If the public demands a hearing, OHS will hold a hearing. If there is no request, OHS may hold a discretionary hearing or may move to the decision or agreed settlement negotiation phase.

Next due date: 5/31/2024

__________

Applicant: Orthopaedic Specialty Surgery Center

Proposal: Transfer of ownership

Docket number: 32697

Application date: 1/10/2024

Current status: OHS is in a 30-day waiting period to see if members of the public demand a hearing.

Next steps: If the public demands a hearing, OHS will hold a hearing. If there is no request, OHS may hold a discretionary hearing or may move to the decision or agreed settlement negotiation phase.

Next due date: 6/7/2024