0082-0316 Project Pages Banner Photo - Reconfiguration of the Route 17 On-ramp to Route 9 Northbound

0082-0316 Project Updates Button News & Resources Button FAQs Button Contact Us Button

Project 0082-0316 Main Street Extension On-Ramp reopening

Click Here to Subscribe to Project Update Emails

Project 0082-0316 DeKoven Drive Off-ramp Closure Alert

Click Here to Subscribe to Project Update Emails

ABOUT THE PROJECT

Planned Construction Activity

Main Street Extension (Summer/Fall 2023)

  • Relocate 17 southbound on-ramp from Main Street Extension.
  • Short-term detours may be required via Pleasant Street and South Main Street.

Main Street Extension (Fall 2023 – Fall 2024)

  • Pedestrian and drainage improvements.
  • Install signal at off-ramp and on-ramp.
  • Milling and overlay.

Route 17 Southbound (Fall 2023 – Summer 2024)

  • Rehabilitate Bridge 00636 – Route 17 NB over Route 9.
  • Traffic maintained - one lane.

Bridge 00638 - Route 9 over Union Street (Winter 2023-Spring 2024)

  • Construct new western spans of Bridge 00638.
  • Reconstruct exit 14.
  • Two lanes of traffic in each direction maintained on Route 9.

Bridge 000638 - Route 9 over Union Street (Summer 2024-Summer 2025)

  • Traffic Shift; Remove existing northbound lanes of Bridge 00638.
  • Construct new eastern section of Bridge 00638.
  • Two lanes of traffic in each direction maintained on Route 9.

Bridge 000638 - Route 9 over Union Street (Summer 2025 - Spring 2026)

  • Construct the new eastern section of Bridge 00638 (northbound).
  • Project Funding Street Sign - Funded by the Bipartisan Infrastructure Law - Building a Better America

Route 9 / Route 17 / Harbor Drive (Summer 2026 - Fall 2026)

  • Construct median barrier along Route 9.
  • Final Mill and Overlay.
  • Open all new lanes to traffic.
  • Close Harbor Drive on-ramp.

Anticipated schedule subject to change due to construction, operations, weather, material availability, and other factors

 

Return to project home page